Executive Summary Report August 1999
Executive Summary Report
August 1999
SMOGCHECK
Statewide
1. Testing Volume
  Total Failed % Fail
a. All Tests: 1,014,322 117,165 11.6%
b. 1st Tests: 848,986 89,398 10.5%
2. Certification Volume
  Total %
a. Total Cert's Issued: 873,471  
b. 1st Tests Rec'd Cert.: 743,217 85.1%
c. 1st Tests No Cert.: 130,254 14.9%
3. 1st Test Failures by Failure type
  Failed % Fail
a. Gross Polluters: 21,613 2.5%
b. All Tailpipe: 64,756 7.6%
c. All Visual: 19,061 2.2%
d. All Functional: 44,047 5.2%
e. Overall: 89,398 10.5%
4. 1st Tests Failures by Program Area
  1st Tests Failed % Failed G.P.s % G.P.
a. Enhanced 539,675 69,134 12.8% 15,853 2.9%
b. Basic 301,944 19,588 6.5% 5,526 1.8%
c. Chg.Owner: 7,298 649 8.9% 225 3.1%
e. Unknown 69 27 39.1% 9 13.0%
d. Total 848,986 89,398 10.5% 21,613 2.5%
5. 1st Test Failures by Station Type
  1st Tests Failed %Failed G.P.s % G.P.
a. REG 489,150 37,328 7.6% 7,796 1.6%
b. GSGR 183,580 17,526 9.5% 3,593 2.0%
c. GPC 67,669 6,204 9.2% 1,788 2.6%
e. TST 104,681 27,736 26.5% 8,267 7.9%
d. Gov.Fl. 2,753 201 7.3% 46 1.7%
f. Bus.Fl. 406 8 2.0% 2 0.5%
g. Referee 747 395 52.9% 121 16.2%
h. Total 848,986 89,398 10.5% 21,613 2.5%
6. Initial Tests by Vehicle Model Year
Model
Year
Initial
Tests
Failed
Tests
%Fail %Fail
Emiss.
%Fail
GP
%Fail
Funct.
%Fail
Visual
1973 13 2 15.4% 15.4% 7.7%    
1974 4,455 745 16.7% 9.0% 4.3% 11.0% 6.9%
1975 3,481 709 20.4% 14.3% 6.0% 11.8% 7.2%
1976 5,682 1,177 20.7% 14.0% 5.9% 12.2% 7.7%
1977 8,556 1,828 21.4% 13.9% 6.1% 13.2% 8.2%
1978 10,082 2,338 23.2% 15.5% 6.8% 14.3% 9.4%
1979 11,546 2,728 23.6% 16.5% 7.5% 14.3% 9.0%
1980 9,103 2,160 23.7% 17.1% 8.2% 15.0% 8.4%
1981 10,941 3,001 27.4% 21.8% 8.4% 15.7% 8.6%
1982 13,094 3,600 27.5% 21.5% 8.2% 15.5% 8.1%
1983 18,321 4,582 25.0% 19.5% 7.0% 13.3% 7.2%
1984 30,321 7,481 24.7% 19.4% 8.0% 12.9% 6.7%
1985 39,453 8,991 22.8% 17.5% 6.8% 11.7% 5.4%
1986 52,302 9,495 18.2% 13.3% 4.8% 9.2% 3.6%
1987 52,852 9,451 17.9% 13.7% 4.6% 8.0% 2.9%
1988 56,513 7,745 13.7% 10.0% 2.7% 6.1% 2.0%
1989 63,193 6,654 10.5% 7.2% 1.7% 4.7% 1.3%
1990 57,541 4,489 7.8% 5.4% 1.1% 3.3% 0.8%
1991 59,188 3,827 6.5% 4.4% 0.8% 2.6% 0.5%
1992 52,229 2,558 4.9% 3.3% 0.6% 1.8% 0.4%
1993 62,616 2,268 3.6% 2.5% 0.4% 1.2% 0.3%
1994 44,397 1,067 2.4% 1.5% 0.2% 0.9% 0.3%
1995 105,127 1,767 1.7% 0.9% 0.2% 0.7% 0.2%
1996 24,463 204 0.8% 0.4% 0.1% 0.4% 0.1%
1997 23,277 153 0.7% 0.4% 0.1% 0.2% 0.1%
1998 18,079 84 0.5% 0.2% 0.0% 0.2% 0.1%
1999 10,669 27 0.3% 0.1% 0.0% 0.1% 0.0%
2000 182 2 1.1% 1.1%      
Total 847,676 89,133 10.5% 7.6% 2.5% 5.2% 2.2%
7. Referee Activity
  Tests Failed % Failed
a. Total Tests 1,548 853 55.1%
b. Tests on GP Veh's 315 140 44.4%
 
OUTCOMES Counts
c. Certificates Issued 907
d. Hardship Extensions 127
e. Waivers Granted 89
Page 1 of 2
Executive Summary Report
August 1999
SMOGCHECK
Statewide
8. Active Stations
  Total Enhanced Basic Chg.Owner Unknown
a. Bus.F. 52 20 31 1  
b. GPC 771 232 469 70  
c. GSGR 1,535 1,101 427 7  
e. Gov.F. 90 82 8    
d. Other 161 26 131 3 1
f. REF 35 20 14   1
g. REG 4,986 2,693 2,232 60 1
h. TST 342 334 7   1
i. Total 7,972 4,508 3,319 141 4
9. Active Technicians
 
License type Count
?? 1
EA 7,203
EB 3,814
TOTAL 11,018
10. ASM Inspection Costs
Station type Count Wtd. Avg. Max. Cost
a. GPC 211 $46.63 98.00
b. GSGR 1,073 $45.97 98.00
c. Other 350 $31.75 75.00
e. REG 2,267 $46.39 98.00
d. TST 430 $48.99 90.00
f. TOTAL 4,331 $46.87 98.00
11. Repair Costs
  Vehicles LIRAP  
  Total $0 - $50 $51 - $150 $151 - $250 $251 - 450 Over $450 Consumer
Avg Cost
Co-Pay
Count
State Pay
Avg Cost
Total
Avg. Cost
a. Statewide 59,602 28,245 16,926 7,029 4,981 2,105       $116
 
b. Enhanced 40,381 19,594 10,926 4,632 3,502 1,504       $117
c. Non-Enh. 16,106 7,127 5,090 2,053 1,277 482       $115
 
d. GSGR 13,985 7,117 3,720 1,582 1,120 381       $106
e. GPC 5,360 1,923 1,250 757 826 528       $188
f. REG 35,962 18,367 10,677 3,826 2,197 783       $96
g. Other 4,295 838 1,279 864 838 413       $220
Page 2 of 2

DW ExSummary.asp -- Started: 12/13/1999 10:32:26 AM, Ended: 12/13/1999 10:35:12 AM